Saving 74% of Project Value: How PHM Is Reviving the Tunu Field
JAKARTA: “There’s no longer an easy way in Mahakam to propose a well package the way we used to, where the risks of marginal wells could cover for one another,” said Adnan Syarafi, speaking at a Technical Program session at the IPA Convention and Exhibition 2026 earlier this year. “Now we have to run a very in-depth, integrated workflow to create projects that are truly resilient,” he added.
With that principle in mind, Adnan, a subsurface development engineer at Pertamina Hulu Mahakam (PHM), and Patria Indrayana reworked the development plan for the Tunu Field in the Mahakam Delta, East Kalimantan. Of the 100 wells in the original plan, 28 were cut. Drilling capital expenditure (capex) fell by 40%, while the project preserved 74% of its value.
Tunu is a mature field whose production is declining naturally. Discovered in 1977 and producing since 1990, the gas-condensate field faces falling reservoir pressure, remaining gas reserves scattered in small pockets (micro-pockets), and high swamp-drilling costs. Through integrated data processing and project-scope screening, PHM trimmed its drilling budget without eroding most of the project’s economic value.
Tunu has a long history as a pillar of national energy supply. Its cumulative production has reached 10 trillion cubic feet (TCF) from more than 1,500 wells, around 30% of the Mahakam Block’s gas output. However, gas prices are tied to global crude oil prices, meaning that profit margins are increasingly squeezed by the high cost of surface facilities and drilling.
Until now, infill drilling at Tunu has followed a geographic sequence. Wells were drilled according to land logistics and ease of access to swamp locations. According to Adnan, that approach is a potential trap in a mature field. Wells with high production potential were often drilled later because access was more complicated, which slowed capital payback and pushed down the Internal Rate of Return (IRR).
“Conditions at the Tunu Field today are no longer easy. We have to optimize limited capital against the remaining reserves through an integrated, iterative screening approach,” said Adnan.
To meet Pertamina’s internal investment criteria, namely a Net Present Value (NPV) above zero, an IRR above 11%, and a Profitability Index (PI) above 1.1, the team overhauled its workflow in two steps.
First, the team merged the Main Zone and the Shallow Zone. The Main Zone is a large, deep zone that is already heavily depleted, while the Shallow Zone is a shallow zone based on seismic anomalies. The two had previously been managed under separate Plans of Development (POD) and were combined into a single development scheme. Shallow zone targets are cheaper and lower-risk, making up about 80% of well candidates, so they can support and share the risk profile of the main zone targets.
Second, the team changed the drilling sequence from geography-based to deliverability-based. Shallow wells with good pressure and short drilling times were prioritized to accelerate cash flow.
As a result, swamp gas production in the first two years of execution rose by 50% to 60% compared with the conventional scenario, and peak production was reached one year sooner. NPV rose 15%, IRR rose 5%, and PI rose 3%, with no additional capital.
The original plan covered 100 wells requiring about USD 300 million in capital, targeting reserves of more than 80 billion cubic feet (BCF) of gas as well as condensate. After each well was assessed on its financial contribution, 28 turned out to be marginal. Their drilling and swamp-construction costs were very high, while the added value was small.
“Wells with moderate reserves but very high capital requirements are naturally taken out of the project. If we force them into the project, they won’t generate added value and will only become a burden on the project as a whole,” said Adnan.
By cutting those 28 wells, PHM was left with the 72 most economically attractive candidates. The move reduced capex by 40%, while it preserved 74% of the project’s value (NPV). The framework has been approved by the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) and by Pertamina internally.
That said, the study still leaves room for further work. The optimization results depend on assumptions about production projections, costs, and schedules, including the assumption that drilling rigs operate without downtime. In his paper, Adnan noted that sensitivity analysis on prices, costs, and rig efficiency has not yet been conducted and is the next item on the agenda. This matters because Tunu’s gas price is tied to crude oil prices, making the project’s economics vulnerable to shifts when prices change.
“The Tunu Field case illustrates a practical, data-driven approach to sustaining the value of mature assets. Smart scope optimization has proven capable of transforming the economics of a mature field from marginal to highly resilient,” Adnan concluded.
- This article is based on the Best Paper study at IPA Convex 2026, presented by Adnan Syarafi and Patria Indrayana of Pertamina Hulu Mahakam.